May
Building Pads
Why do some lots require a building pad when others don’t?
An average subdivision lot does not require the construction
of a pad, typically it will be flat and level. The finish
floor elevation (finished height of the homes floor) need
only be 12” higher than the curb. Irrigated lots will
almost certainly need a pad that raises the finish floor
elevation from 18”-20” above the yard, some
developers will sell these lots with the pads already installed.
Lots that are situated on sloping grades as found in the
foothill areas around Phoenix normally require pads, these
type lots can benefit from a “cut & fill”.
A cut and fill is where the higher portion of the lot is
cut down below grade, that material (if suitable for compaction)
can be used to raise up the lower section of the lot. On
more severe grades retaining walls will also be used.
Compaction Tests
Once a pad is completed a soils engineering company will
be called to test the pads compaction rate. The engineer
will test the pad in 2-3 different locations. Most cities
require a pad have a compaction rating of 95% or better,
a letter will be issued listing the compaction rate. When
calling for a house footing inspection the city inspector
will ask to see the compaction report before approving the
footing inspection.
Certified Pads
Recently more cities are requiring a pad to be certified
by a soils engineering company before allowing the house
to be built. The compaction test as previously mentioned
only tests the soils upper layer, apx. 12” down, so
if your pad is 4’-5’ high (as measured from
native soil) there is no guarantee how well the soil is
compacted below. With a certified pad, a soils report is
used to determine the characteristics of the existing native
soil. Most developers will have completed this report and
have it available for the engineer, if not you must hire
the engineer to go to the lot with a backhoe or drill rig
and perform various tests and create a soils report, this
will usually cost about $1,800. The engineer uses the information
from the soils report to determine requirements for how
the pad should be built.
During pad construction its typical for the engineer to
come to the site and perform compaction tests on every 12”
of soil added to the pad (these are called “lifts”)
Following a final compaction test and verification that
the pad was built correctly the engineer will issue a letter
certifying the pad. The on-site testing and certification
letter will run between $600 and $1,200 depending on the
size and scope of work
Civil Engineer
Most cities will require that a civil engineer create a
grading and drainage plan on all but the very basic of pads.
This plan typically will have a topographical survey, a
flow study on any washes that cross your lot, and a plan
to take the runoff water safely through and away from your
lot. The cost of a grading and drainage plan can run between
$2,500 and $4,000. It’s always a good idea to meet
with the cities civil engineer to find out if this plan
will be required. If not in a city but in a county area
you can call the Maricopa county flood control for assistance.
back to top
* The information contained in this
“tips” section is to be used as a general guide
only. When making decisions about your project a professional
should be consulted using the specific information that is
unique to your project.